Town of Estes Park Prospect Mountain Water Distribution System Construction Project Updates

**Winter Conditions** Wagner Construction will not work during adverse weather conditions. If you have an urgent question about specific crew impacts due to weather, please contact Steve Jensen at 970.646.2033

three-week Schedule

Service Line Schedule

Project updates

**Construction Status open house for the entire project area will be held on January 30th at 5:30pm at the Town Hall**
Wagner Construction continues to have six crews working simultaneously in different project areas. Crews 1, 2, 3 and 4 are installing the water mains while crews 5 and 6 are working on individual service lines. The crews may shift around depending upon changes in the field to Wagner’s approach to work.

Water Main Construction Areas:
Upper Venner – Prospect Mountain Drive (no excavation work required for the project between Venner Ranch and Peak View)

Venner Ranch Road – Construction crews will start on the individual water service connections on Venner Ranch Road in January

Prospect Mountain Court – Construction crews will start on the individual water service connections on Prospect Mountain Court by the end of January

Koral Heights:

  • Prospect Mountain Road towards Peak View Drive
  • Juniper Drive towards Devon Drive
  • Curry Drive to the East and towards Vista View Lane.
  • Koral Court, Tall Pines Road, and Vista View Lane – Construction crews will start to install water mains for these areas in January

Click to view the full January Public Update

Water Main Construction Areas:
Upper Venner – Prospect Mountain Drive (no excavation work required for the project between Venner Ranch and Peak View)

Koral Heights – Construction starting in Koral Heights (generally North to South)

Tank Site: Construction focused on tank site excavation this month.

Water Main Construction Areas:
Upper Venner – Prospect Mountain Drive

Tank Site – Construction focused on tank site excavation this month.

Prospect Mountain Drive – Construction crews are working from the top of Prospect Mountain down to Upper Venner Rd.

Ranch Circle – Crews are finishing the water line testing and will start on the individual service connections early August.

Little Prospect – We are working to complete the water line main in the area over the next couple of weeks.

The contractor began work around the future tank site in January. Thus far, access to the tank has been cleared, and a road has been “roughed” in. At the location of the tank, geotechnical confirmation of sub-surface conditions is pending.

In late April/early May, the contractor will begin construction on the tank and adjacent instrumentation building. Construction of the new water mains will start in May. Most service line connections will be completed in 2024, with the exception of a few connections in late 2023.

Last month, the Town of Estes Park held a Zoom presentation about the project for the Upper Venner Ranch Estates Property Owner’s Association. The presentation slides can be viewed at the link below.

Upper Venner Ranch POA Presentation – March 16, 2023

The Prospect Mountain Water Improvement project is currently out for bid. Once contractors have submitted proposals in late Summer/early Fall, Town staff will hold an informational meeting with the public to discuss costs and a preliminary schedule for construction. Residents may notice some activity in the project area as contractors prepare estimates during the bid process, however actual construction work will not begin without advance resident notification. A rough, preliminary estimate for the start of construction is in mid-Fall of 2022. Work is anticipated to be ongoing for two years.

Map of prospect mountain

Overall Schedule

Frequently asked questions
Please visit our Frequently Asked Questions Page.

Project documents 
Click to view project drawings.

Contact information

Local Neighborhood Liaisons

Lower Venner (Ranch Circle)
Austin Condon
awcflash@aol.com 

Upper Venner (Prospect Mtn)
Neil Alexander
nalexander@cokesbury.com

Koral Heights
Mark Hewitt
markandrewhewitt@aol.com

Curry Drive
Ann Wise
annwise@bellsouth.net

JVA, Inc.

JVA Project Manager
Mandy Rasmussen, PE
970.420.9636
mrasmussen@jvajva.com

JVA Project Engineer
Maddy Turner
708.646.7937
mturner@jvajva.com

JVA Resident Project Representative
Andrew Steinhauer

Town of Estes Park

Project Manager – Utilities
Jacqui Wesley
970.577.3611
jwesley@estes.org

For immediate service questions or concerns, contact the Town of Estes Park Water Division by calling or scheduling an appointment at: Monday through Friday, until 3:30 pm: (970) 577-3619 After hours and weekends: (970) 577-3626

Wagner Construction, Inc.

Construction Manager – in Estes Park
Steve Jensen
970.646.2033
s.jensen@wagnerconstructioninc.com

Construction Manager
Maurisio Ayala 
720.470.0019
m.ayala@wagnerconstructioninc.com

Scroll to Top